  • First phase of the Project (1MW) was setup in 2003 on 50 cusecs water allocated to AJK for Irrigation of Khari and Panjeri areas downstream Mangla Dam.  
  • The 2nd Phase of the Project (3.5 MW) is being constructed on the additional allocation of 126 cusecs water allocated to AJK by government of Pakistan for drinking and industrial demand of Mirpur City under Mangla Dam Raising agreement signed and executed in June 2003.  

Visit the Link for more detail. thanks

https://drive.google.com/file/d/1xIZw08-q0HV1NBLOS_1zC048J1WRMpui/view?usp=sharing

Comments

Popular posts from this blog

Balancing Canal dept

Balancing Canal depth Balancing Canal depth: "Balancing  canal  depth  comes when the canal is in partially embankment and partially in cutting.It is the  depth  of the canal(H) which gives equal amount of filling(i.e earth required for formation of Banks) and cutting(i.e earth from digging). " Balancing canal depth comes when the canal is in partially embankment and partially in cutting.It is the depth of the canal(H) which gives equal amount of filling(i.e earth required for formation of Banks) and cutting(i.e earth from digging). For a given cross-section of a canal, it has only one balancing depth. For this depth the canal sectional will be economical. B= Bed width. b1,b2= width of embankment of left and right side respectively. d= excavation depth. h= embankment height. H=height of embankment from the bed of the canal.     X- sectional area in cutting =Bd+sd 2       X- sectional area in...

Engineering Drawing Basic Tips & Rules, Lettering Dimensions etc